Tacony-Palmyra Bridge truss and arch span maintenance work(per BCBC):
Arch Span:
1. The proposed reduction in clearance is three (3) feet.
2. Work is scheduled to commence on March 21, 2019 and be completed on January 2, 2020. However in order to provide the Contractor access to other waterway spans, the installed underdeck platforms shall remain in place until April 27, 2020.
3. The work above the deck is not listed since it has no effect upon the maritime community.

Palmyra Truss Spans:
1. The proposed reduction in clearance is four (4) feet.
2. Work is scheduled to commence on March 21, 2019 and be completed on November 6, 2019. However in order to provide the Contractor access to other waterway spans, the installed underdeck platforms shall remain in place until December 3, 2019.
3. As discussed on February 5, 2019, it is expected that there would be no actual impact to commercial maritime traffic for these specific spans.