Delaware City (Bulkhead Shoal) Channel maintenance dredging(per Norfolk Dredging):
The Dredge Essex should arrive at Delaware City Channel on or about Thursday, DEC 6th and begin pipeline laying operations thereafter. We will be dredging in their entrance channel from Stations 67+00 to 95+00 (which is just south of the entrance to Delaware City Marina) and also at Pier 3, which is the northernmost pier at the refinery. As usual, we will be standing by on VHF 13 and 16. feel free to call if you have any questions.